On April 15, CCCC Third Harbor Engineering Co., Ltd. won the bids for the surface channel and outlet project of Unit 3 and 4 of Tianwan Nuclear Power Plant in Lianyungang, with a contract value of 97.91 million yuan and a construction period of 771 days.

Located in Tianwan, Lianyun District, Lianyungang, the project involves three sub-projects: surface channel jetty, outlet and apron, and channel excavation. With a length of some 1,311 meters, the jetty includes a connecting section and a standard section. The channel has an excavation capacity of 880,000 cubic meters.

The project will lay a solid foundation for the expansion of Unit 3 and 4 of Tianwan Nuclear Power Plant.