VIDEO: Trafalgar Wharf Dredging in Full Swing

A maintenance dredging scheme at the Trafalgar Wharf area in Portsmouth is nearing its completion.

This dredging project started on July 4 and is expected to last around 4 weeks, according to the Queen’s Harbor Master Portsmouth.

The completion date will be weather dependent.

The works are being carried out by ML Dredging Ltd using the backhoe dredger “Witton II” with the spoil loaded onto self propelled split hopper barges “Split Two” and “Split Three”.

Disposal of dredged material is taking place at the Nab Spoil grounds.

Check out this short video of the Trafalgar Wharf dredging operations:

Share this article

Follow Dredging Today

Events>

<< Oct 2019 >>
MTWTFSS
30 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3

Eastern Chapter WEDA Fall 2019 Conference

Wednesday (10/16/19) afternoon will start the program with an opportunity to take the Dredging 101 course.

read more >

DREDGING FOR SUSTAINABLE INFRASTRUCTURE INDIA

At this 1-day conference, you will experience what it means to apply this new approach in practice.

read more >

CEDA Dredging Days 2019

The conference is well-attended by professionals representing the entire cross-section of the dredging field…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply