Phase 4 of the North Portsea Island Coastal Flood Defense Scheme

Image source: ESCP

The Eastern Solent Coastal Partnership (ESCP) recently presented additional data on the North Portsea Island Coastal Flood Defense Scheme.

The new coastal defenses have been designed to reduce the risk of coastal flooding and erosion to the area over the next century.

According to the ESCP, the implementation of the project has been split into five phases, two of which are complete and the third phase is under construction.

 

The North Portsea Island Coastal Flood Defense Scheme:

  • Phase 1Anchorage Park: the construction of 1.4km of earth embankment with rock revetment toe completed in 2016 at a cost of approx. £5m;
  • Phase 2Milton Common: the construction of 1.5km of set back earth embankments and rock revetment structure, completed in 2016 at a cost of £3m;
  • Phase 3Tipner Lake: is the construction of 1.9km of a seawall which commenced April 2017 and is programmed for completion by the end of Autumn 2019;
  • Phase 4Eastern Road and Kendall’s Wharf: the construction of a seawall with road raising at the entrance to Kendall’s Wharf;
  • Phase 5Ports Creek: 1.3km of earth embankment with a rock revetment toe to be constructed in 2023 and 2024.

Phase 4 is the next phase of works with a combination of two distinct sections: Kendall’s Wharf and Eastern Road. The full length of the frontage is 2.4km (300m for Kendall’s Wharf and 2.1km for Eastern Road), reported the ESCP.

Construction is due to start in September 2019, with completion of the construction works by October 2022 excluding landscaping works which will be completed by February 2023. The new defenses at Kendall’s Wharf will tie in with those built at Anchorage Park in 2016.

The ESCP also added that the first 150m of new defenses will be a raised earth embankment with a continuation of the 3m wide coastal path. This embankment will tie into the area of road raising landward of Kendall’s Wharf, where the road will be raised by approximately 1m. South of the road will be 150m of steel sheet pile wall and will tie into the coastal defenses at Eastern Road.

At Eastern Road the works will include the demolition and removal of the existing seawall in the southern section of the site, and the construction of a vertical reinforced wall with a stepped revetment.

In the northern section, the existing seawall will be encased and the existing path behind the seawall reconstructed. Landscaping works will be carried out to enhance this much loved coastal region including new access points to a public footpath, four slipways and three access steps.

 

Share this article

Follow Dredging Today

Events>

<< Aug 2019 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31 1

Eastern Chapter WEDA Fall 2019 Conference

Wednesday (10/16/19) afternoon will start the program with an opportunity to take the Dredging 101 course.

read more >

10TH Annual Conference Dredging in India

The conference will focus on strategies and solutions to meet the future dredging requirements…

read more >

Australasian Coasts and Ports 2019

Conference Theme “Future directions from 40°S and beyond” reflects the increasing awareness about the need to find suitable…

read more >

PORTS Conference

The PORTS Conference series is internationally recognized as an outstanding opportunity to network with…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply