Post Florence Renourishment Project Moves Forward

The Carteret County announced yesterday that Reach 3 (east Indian Beach and Salter Path) under the Post Florence Renourishment Project was completed last Sunday.

Officials also added that the first load of sand was delivered to Reach 2.

According to the update, beach nourishment activities are now progressing eastward from the 2nd submerged pipeline landing, and will be “flipped” westward once the eastward run is completed. Also, the submerged line for Reach 1 in Emerald Isle has been installed near 16th Street.

The Post Florence scheme – awarded to the Great Lakes Dredge & Dock Company (GLDD) – will utilize 945,446 cubic yards of sand obtained from the Offshore Dredged Material Disposal Site (ODMDS) associated with Morehead City Federal Navigation Project.

Emerald Isle (EI), Indian Beach (IB), and the unincorporated area of Salter Path (SP) will receive 617,131 cy, 271,905 cy, and 56,410 cy, respectively along 5.2 miles of shorelines.

The Post Florence Project is scheduled to be completed by April 30, 2019.

 

Share this article

Follow Dredging Today

Events>

<< Mar 2020 >>
MTWTFSS
24 25 26 27 28 29 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply