Because of the bad weather, construction works on the Phase II of the Post Florence Renourishment Project were briefly paused last Sunday, according to the Carteret County Shore Protection Office.
As reported, the hopper dredge Ellis Island went into safe harbor to avoid the rough seas and took this opportunity to refuel.
The work is set to start back today in West Emerald Isle where the crews have approximately 6,800 linear feet to go.
The contractor is expecting to complete the eastern push from “Line 7” on April 16th, flip the elbow and head west on April 17th and perhaps complete the reach and project on or about April 23rd.
The contract for the phase II of the Post Florence Renourishment Project was awarded to Great Lakes Dredge & Dock (GLDD) back in 2019.
Overall, the phase II will utilize 1,995,000 cubic yards (cy) of sand obtained from the Offshore Dredged Material Disposal Site (ODMDS) associated with Morehead City Federal Navigation Project.
Phase III of the Post-Florence Renourishment Project is tentatively scheduled for winter 2020-2021 and will encompass Central and Western Emerald Isle.
List of related news articles
-
Posted: 11 days ago
Dredge Liberty Island to start Phase III of the Post-Florence project in late January
The Post-Florence Renourishment project sponsors (Carteret County and Emerald Isle), Engineers (Moff...
Posted: 11 days ago -
Posted: about 1 month ago
Florence renourishment project – PHASE III
Great Lakes Dredge & Dock (GLDD) is about to begin preparations for the Phase 3 of the Post-Flor...
Posted: about 1 month ago -
Posted: 4 months ago
Officials discuss Phase 3 of the Post-Florence project
Great Lakes Dredge & Dock Corporation COO Dave Simonelli recently met with Greg Rudolph, Shore P...
Posted: 4 months ago -
Posted: 4 months ago
GLDD secures $118.8 million in new contracts
Great Lakes Dredge & Dock Corporation (GLDD) announced today the receipt of several major dredgi...
Posted: 4 months ago