Levee Repairs along Carbon River

Construction to restore flood protection to the Carbon River levee system near the City of Orting is now underway with the U.S. Army Corps of Engineers repairing 1,520 feet of damaged levees at five individual sites for about $1.7 million.

All in-water work is scheduled to be complete by August 31, the end of the “fish window” when construction crews can work in the water with the least amount of disruption to fish. Above-ground work is expected to last through mid-September.

We have a challenging schedule, but we want to restore these levees to their designed level of flood protection before the fall flood season,” said Daryl Downing, the Corps Carbon River levee project manager. 

Damage to the levees occurred during high-flow events in November 2014 and January 2015. Repairs will address scour, erosion, loss of riprap armor, gravel filter and embankment material in some locations. Levee toes will be reconstructed, slopes regarded and armored with a blanket or riprap to protect against river flows.

 

Share this article

Follow Dredging Today

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply