The U.S. Army Corps of Engineers, Norfolk District, has just announced that the Willoughby Spit and Vicinity beach nourishment project is now 69% complete.

Nine weeks into the project, the Corps contractor Great Lakes Dredge and Dock Company has placed over 829,000 cubic yards of sand onto the beach.

“We now have three dredges working on site,” USACE said in its latest update.

In total, it will take around 1.2 million cubic yards of sand to complete this 34.5 million worth beach nourishment project.

If all goes according to schedule, USACE expects to complete the beach nourishment this May.

Share this article

Follow Dredging Today

Events>

<< Aug 2019 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31 1

Eastern Chapter WEDA Fall 2019 Conference

Wednesday (10/16/19) afternoon will start the program with an opportunity to take the Dredging 101 course.

read more >

10TH Annual Conference Dredging in India

The conference will focus on strategies and solutions to meet the future dredging requirements…

read more >

Australasian Coasts and Ports 2019

Conference Theme “Future directions from 40°S and beyond” reflects the increasing awareness about the need to find suitable…

read more >

PORTS Conference

The PORTS Conference series is internationally recognized as an outstanding opportunity to network with…

read more >

Jobs>

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply