Work on K. Maafushi Land Reclamation and Shore Protection project is well underway, with overall 78% project progress, the Maldives Transport and Contracting Company (MTCC) informs.

Revetment works for the project is currently ongoing, the company stated.
The K. Maafushi Land Reclamation and Shore Protection project consists of; 25 hectares of land reclamation work; construction of a 1,100m rock boulder revetment.
The project design is based on bringing a solution to the high demand of residential plots on the island. The estimated value of the project is $6.4 million, said MTCC.
The equipment for this project was mobilized on 17th September 2019.
Photo: MTCC photo
List of related news articles
-
Posted: 1 day ago
MTCC wins Felivaru Harbor contract
Maldives Transport and Contracting Company (MTCC) and the Maldives’ Ministry of National Plann...
Posted: 1 day ago -
Posted: 4 months ago
Guraidhoo land reclamation moves ahead
Work on K. Guraidhoo Land Reclamation and Shore Protection Project is moving forward according to sc...
Posted: 4 months ago -
Posted: 10 days ago
Work on Ihavandhoo Harbor moves ahead
Development work of Ha. Ihavandhoo Harbor is well underway, with overall 35% project progress to dat...
Posted: 10 days ago -
Posted: 6 months ago
Maafushi land reclamation wraps up
Land reclamation component of K. Maafushi Land Reclamation & Shore Protection project is now off...
Posted: 6 months ago