Port of Aberdeen marks penultimate construction milestone

The handover from construction to operations for Dunnottar, Crathes and Castlegate (East) Quays was completed last week.

portofaberdeen.co.uk

More than 60% of Port of Aberdeen’s £400 million South Harbour development is now operational, marking the penultimate construction milestone in this transformational project.

portofaberdeen.co.uk photo

The handover from construction to operations for Dunnottar, Crathes and Castlegate (East) Quays was also completed last week.

Castlegate (West) is scheduled to open in December 2022 and the remaining Balmoral Quay will be brought into service in Q2 2023, making Aberdeen the largest berthage port in Scotland.

More than 25 vessels have berthed at Aberdeen South Harbour during a ‘soft start’ to operations which began in July.

A host of new and existing customers have already benefitted from Aberdeen’s safe and efficient port services and generous quayside space.

The Port’s existing North Harbour offers world-class facilities and infrastructure, and the South Harbour expansion will:

  • add 1.4km of deepwater berthage,
  • accommodate ships up to 300 metres in length,
  • incorporate extensive heavy-lift zones up to 15 tonnes/m2,
  • offer 125,000m2 of flexible laydown space and expansive project areas.

South Harbour is the largest marine infrastructure project underway in the UK and an asset of national strategic significance, included in the Scottish Government and UK Government’s NPF3 planning framework and Scotland’s draft NPF4.