Russia: Jan de Nul Completes First Phase of Sabetta Port Dredging

The Federal Marine and River Transport Agency has announced that Jan de Nul has completed the first phase of dredging operations in Sabetta Port.

From August 2 until October 9, the company dredged 10 mln cbm of material.

The dredging project is scheduled for completion in 2016. During the 2014-2016 period, the fleet of Jan De Null is expected to dredge up to 70 million cbm of material. The seaway canal will be 49 km long, 295 m wide and 14 m deep.

Port Sabetta will be capable of handling gas carriers with length of up to 300 m, width of up to 50 m and cargo tanks capacity of up to 170,000 cbm.

Press Release, October 14, 2013

Share this article

Follow Dredging Today

One thought on “Russia: Jan de Nul Completes First Phase of Sabetta Port Dredging”

Comments are closed.

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

Navingo Career Event 2020

The Navingo Career Event is Europe’s biggest career event for the maritime,…

read more >

Jobs>

Dredging jobs in Abu Dhabi at NMDC

National Marine Dredging Company “NMDC” aims to be the largest dredging player in the Arab’s Gulf region...

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below....

apply

Looking to fill a job opening?

By advertising your job here, on the homepage of DredgingToday.com, you'll reach countless professionals in the sector. For more information, click below...

apply