Isdhoo Harbour development moves forward

Work on the L. Isdhoo Harbour development scheme is currently underway, with overall 85% project progress.

MTCC

According to the Maldives Transport and Contracting Company’s latest update, they have already completed construction of the quay wall.

MTCC photo

Scope of works for this project includes:

  • dredging and excavation operations of 27,129cbm;
  • construction of a 230m quay wall;
  • a 208m breakwater and a 98m revetment.

Additionally, creation of 1,560sqm of paved area and installation of harbor lights will also be undertaken.

The value of the project is MVR 34.7 million ($2.2 million).